Sunday, June 8, 2008

The Building Phases

The Building Committee at Peki Church has outlined the following plan for completing the church. Where would you like to fit in?


Phase 1
  • Concrete work
  • Block work
  • Joinery – door frames and window frames with security bars
  • Metal work – aluminum louver carriers
  • Glazing – glass louver blades
Phase 2
  • Concrete work
  • Block work
  • Carpentry
  • Joinery
  • Metal work - aluminum louver frames
  • Glazing - glass louver blades
Phase 3
  • Plumbing installations - plumbing, piping, and sanitary fittings
  • Electrical - installation of electric conduit and cables
  • Finishing - wall rendering, slab screeding, plywood ceiling
Phase 4
  • Electrical - installation of ceiling fans, flourescent lights, switches, and sockets
  • Finishing - floor tiling, terrazzo, and wall tiling
Phases 5 & 6
  • Finishing - painting of wals
  • External works
Estimated total budget: $130,000 (US dollars)